A 50 kW solar plant generates roughly 80,000 units a year — about 215 to 225 units a day — at an indicative installed cost of ₹21,00,000 to ₹26,50,000. This is industrial territory: single-shift manufacturing units, large hotels, hospital campuses and warehouses with refrigeration.

Indicative cost

₹21,00,000–₹26,50,000

installed, before tax treatment

Generates

215–225

units per day in Jaipur

Payback

3 to 4

years, at the tariff modelled below

At 50 kW the project has three engineering phases that a smaller job does not: a structural assessment that may require reinforcement, a load and protection study of the existing electrical infrastructure, and a commissioning programme that produces measured results rather than a functional confirmation. Skipping any of them is how a plant ends up underperforming with no baseline to argue from.

Specification

50 kW solar system — cost, output and requirements

Every figure below is modelled for Jaipur-region conditions on a clean, unshaded, correctly designed array. They are planning numbers, not a quotation.

50 kW solar system specification, cost and generation summary
System capacity50 kW
Indicative installed cost₹21,00,000 – ₹26,50,000
PM Surya Ghar subsidyNot applicable — the scheme covers residential connections only
Tax treatmentAccelerated depreciation available to profit-making entities
Daily generation215 to 225 units on an average day
Annual generationAbout 80,000 units
Roof area requiredAbout 3,600 sq ft, shade-free
Solar panels90 to 92 modules at present-day panel wattage
Indicative annual savingAbout ₹7,20,000
Simple payback3 to 4 years

Pricing is an indicative installed-cost band, not a quotation. Roof type, structure, mounting height, cable run length and module availability all move the figure, and a firm price is issued only after a site survey. Generation assumes roughly 1,600 kWh per kWp per year; savings assume the tariff stated on this page. Subsidy figures follow PM Surya Ghar as currently notified — verify current rates at pmsuryaghar.gov.in.

In practice

What a 50 kW system actually powers

Capacity is easy to quote and hard to picture. This is what the generation covers in a real building.

  • A single-shift manufacturing unit
  • A large hotel or resort property
  • A hospital or institutional campus building
  • A warehouse with refrigeration and handling equipment

Structural assessment comes before layout

Industrial shed roofs vary enormously in quality. Purlin spacing, section capacity, sheet condition and existing loads all decide what an array can weigh and where it can sit. We survey the structure before drawing a layout, not after.

Where a roof will not carry a ballasted array, the answer is elevation, reinforcement, or a ground-mounted plant on adjacent land. On a site with spare land the ground-mounted option is often better engineering anyway: optimum tilt, easy cleaning access and no structural compromise for twenty-five years.

The economics for an industrial consumer

At an industrial tariff around ₹9 a unit with strong self-consumption, 80,000 units a year is worth roughly ₹7,20,000. Against an installed cost of ₹21 to ₹26.5 lakh, that is a simple payback of three to four years before any tax treatment.

Accelerated depreciation improves the post-tax picture further for a profit-making entity. We provide the generation model and the cost; your finance team should run the depreciation and cash-flow treatment on top of it, because that calculation depends on your tax position rather than on the plant.

Tie-in and production continuity

Roof installation happens while you operate normally. The genuine interruption is the electrical tie-in, which needs a planned outage. We pre-fabricate and pre-test as much as possible so that outage is measured in hours, happens once, and lands inside a shutdown window you have already planned.

Commissioning then produces the documentation that makes the plant maintainable: as-built drawings, string test results, insulation resistance and earth continuity records, inverter configuration records, the O&M manual and a measured performance baseline.

No obligation, no cost

Before you buy a 50 kW system, get the numbers

Solar is a twenty-five year decision made on a single afternoon's information. Before you commit to a system in Jaipur, we will give you the numbers to decide with — and tell you if the answer is that solar is not worth it on your roof.

  • Free solar consultation

    A conversation with an engineer, not a salesperson — what your roof and your load can actually support.

  • Free site survey

    Roof measurement, structural check and a seasonal shadow analysis carried out at your property.

  • Free savings report

    Your last twelve months of bills modelled against real generation figures for your location.

  • Free ROI calculation

    Payback period, lifetime savings and the honest sensitivities — including what happens if tariffs stay flat.

  • Free subsidy assessment

    What you may qualify for under PM Surya Ghar, and what the net cost is after it lands.

50 kW solar system — frequently asked questions

What is the cost of a 50kW solar plant?

Indicatively ₹21,00,000 to ₹26,50,000 installed in Rajasthan. Where a project falls within that band depends on roof structure and any reinforcement needed, mounting type, cable run lengths, the condition of the existing LT infrastructure and whether the site needs a ground-mounted rather than rooftop solution.

What is the payback period on a 50kW industrial solar plant?

Typically three to four years at an industrial tariff around ₹9 a unit with strong daytime self-consumption, before accounting for accelerated depreciation — which improves the post-tax position further for a profit-making entity. The variables that move payback most are your shift pattern, your tariff category and how much generation you self-consume rather than export.

Will installation disrupt my factory's production?

Roof installation proceeds while you run normally. The only real interruption is the electrical tie-in, which needs a planned outage of a few hours, scheduled into a shutdown window you have already planned. We pre-fabricate and pre-test so that window stays short and is needed once rather than repeatedly.

Can my factory shed roof take a 50kW array?

That is a structural question we answer with a survey before quoting a layout — purlin spacing, section capacity, sheet condition and existing loads all decide it. Where the shed will not carry a ballasted array we design elevation or reinforcement into the project; where the site has spare land, a ground-mounted plant is often the better engineering answer anyway.